There appears to be a fairly obvious bug in the Task View heading totals in Pocket Informant 4.5.10.

The total shown (e.g. 'All Dates: 49'), always includes Completed tasks, whether or not Include>Completed is enabled. By contrast, the total correctly reflects Include>Undated.

This error arises in all 'groups' (All Dates, In Progress, Start/End Today, etc.)

I've reported this to PI Support.

Newcomer to PPC, using iPAQ 2210 (PPC 2003).

--
Terry, West Sussex, UK

terrypin
09-13-2003, 01:54 PM
Closing off this thread, I'm reporting that PI Support confirmed that as a bug.